Planning Intelligence
Draft · Not Ready

Decision topic

Northstar Demand Execution

Decision prep in progress

Facts on the table

Demand

Observed fact

1,200 units · $12.0M

Base production

Calculated result

700 units · $7.0M

Components

Observed fact

850 units · $8.5M

Root cause

Analyst judgment

Demand was accepted into the forecast before cross-functional operational validation. Finance, sales, purchasing, and operations each held individually reasonable information — a confirmed customer request, committed component volume, and a fully loaded production plan — that had not been reconciled.

Recovery options

0 of 3 resolved · validated evidence only

Overtime

Not investigated
Effect
+150 production units · +$1.5M revenue capacity
Cost
$180K cost
Dependency
Requires additional quality inspection

Not yet investigated — excluded from the executable plan.

Weekend shift

Not investigated
Effect
+150 production units · +$1.5M revenue capacity
Cost
$300K cost
Dependency
Staffing must be validated

Not yet investigated — excluded from the executable plan.

Supplier expedite

Not investigated
Effect
+200 control modules · components rise 850 → 1,050
Cost
$100K cost
Dependency
Does not directly add production revenue

Not yet investigated — excluded from the executable plan.

Outsourcing

Not applicable — no capacity
Effect
0 units this planning window
Cost
No cost incurred
Dependency
Partner qualification timing
07_Operations_Commentary.docxValidated business response

07_Operations_Commentary.docx, Recovery Options section, paragraph 4

Outsourcing assessment result

External partner qualification requires 10–12 weeks, including first-article inspection.

Qualification cannot complete within this planning window.

Outcome: 0 units available for February — not feasible.

Assessed — no capacity available this planning window. Does not block readiness.

Likely reviewer questions

Same facts, three different lenses. Prepared responses live in the Executive Brief.

Focus: Forecast integrity, financial impact, confirmed vs. assumed

  • How much of the $12.0M is confirmed executable versus assumed?
  • What changed between the original forecast and this recommendation?
  • Which figures are observed facts and which are assumptions?
  • What is the profit impact of the mitigation plan?

Executable plan

Calculated result

Updates from validated evidence only.

Demand
1,200 units · $12.0M
Production capacity
700 units
Component support
850 units
Executable
700 units · $7.0M
Unsupported forecast
$5.0M
Binding constraint
Production capacity
Mitigation cost (confirmed)
$0

Executable = minimum of demand (1,200), production units, and component units, at $10,000 per unit.

Profit impact

Unknown

Profit impact cannot yet be calculated reliably; approved gross-margin evidence is required.

Recommendation

Recommendation locked. Validate the recovery options first — unvalidated capacity never enters the executable plan.